APH DRYWALL LTD.
Drywall & Insulation Contractor

Services

One scope, in work order. Insulation first, then boarding, then taping & finishing — so nothing is done out of sequence and the finish is ready for paint.

Wall explorer — tap a layer

Tap Insulation, Boarding, or Taping & Finishing and that layer lifts out of the wall. Diagram, not a project photo.

Insulation
Board
Tape & Finish

Insulation installed as the first step of the drywall sequence. It is checked for coverage and continuity before boarding starts, so boarding does not hide an unfinished insulation scope.

01 — Insulation

Insulation installed as the first step of the drywall sequence. It is checked for coverage and continuity before boarding starts, so boarding does not hide an unfinished insulation scope.

Good for: houses, multi-unit builds, and commercial interiors where the wall build-up must be complete before boarding.

02 — Drywall Boarding

Drywall boarding installed, fixed, and prepared for taping. Joints are set out so taping can follow cleanly, and openings and corners are left ready for finishing work.

Good for: new interiors, remodelled rooms, and repeated units where consistent boarding keeps the schedule on track.

03 — Drywall Taping & Finishing

Taping and finishing to a clean, paint-ready surface. Joints and fasteners are treated, corners are finished, and surfaces are left ready for the painter — without rough joints or visible patchwork to slow the next trade.

Good for: any interior where the final wall finish will be seen and judged at walk-through.

Secondary work

ServiceHow it fits
TextureSecondary finish, after taping, where a textured surface is specified.
Spray foamSecondary insulation option, discussed as part of the wall build-up scope.
PaintFinal, secondary item only — not a lead service, and not a separate paint slide or page.

Finish levels — a plain reference

Standard drywall finish levels, for reference only. The level for a project is agreed when the scope is quoted.

LevelWhat it means
Level 0No taping or finishing.
Level 1Tape embedded in joint compound.
Level 2One coat over tape and fasteners.
Level 3Two coats, ready for heavy texture or paint where minor marks are acceptable.
Level 4Three coats, the usual paint-ready finish.
Level 5Level 4 plus a skim coat for the smoothest finish under critical light.